FINISHING PROCEDURE

After the construction is completed for the factory to be put into use, the following procedures are required:
| No. | Content | Duration |
| 1 | Checking of connection (traffic, water supply, wastewater,…) | 15~30 days |
| 2 | Fire protection test | 15~60 days |
| 3 |
Acceptance and put into use |
15~60 days |
After completing the procedures, the industrial park management board will issue the certificate of acceptance and put into use.