FINISHING PROCEDURE
After the construction is completed for the factory to be put into use, the following procedures are required:
No. | Content | Duration |
1 | Checking of connection (traffic, water supply, wastewater,…) | 15~30 days |
2 | Fire protection test | 15~60 days |
3 |
Acceptance and put into use |
15~60 days |
After completing the procedures, the industrial park management board will issue the certificate of acceptance and put into use.
Comments
0 Likes
Post a Comment
You must be logged in to post a comment.