| No. |
Content |
Duration (days) |
| 1 | Approved detailed planning 1/500 | 45 |
| 2 | Verification of environmental impact assessment reports | 45 |
| 3 | Fire protection appraisal | 30 |
| 4 | Basic design appraisal dossier | 30 |
| 5 | Technical design appraisal dossier | 30 |
| 6 | Application for construction permit / | 30 |
Some of the above steps can be done in parallel to shorten the time for approving legal proceedings and normally it will take about 60 to 120 days.