CONSTRUCTION PERMIT APPLICATION PROCEDURE
Construction permit is a legal document issued by a functional agency before starting the work. Below are the conditions and procedures for applying for a construction permit.
No. |
Content |
Duration (days) |
1 | Approved detailed planning 1/500 | 45 |
2 | Verification of environmental impact assessment reports | 45 |
3 | Fire protection appraisal | 30 |
4 | Basic design appraisal dossier | 30 |
5 | Technical design appraisal dossier | 30 |
6 | Application for construction permit / | 30 |
Some of the above steps can be done in parallel to shorten the time for approving legal proceedings and normally it will take about 60 to 120 days.